Progress of works in Miamba Village Works are progressing well in Miamba Village. Herebelow progress of works. Masjid - Completed plasterering the walls and beams. - Started painting 1st coat internally and externally. - Paving done around the Masjid. - Water tanks mounted to their stand and connected to the down pipe, pending to piping connection to the ablution areas. In fact they had even collected water and filled over the showers last week. - Tiling done to the entire ablutions except for the finishing works to it. - Door and window shutters installed.   Madrasah Classrooms. - Completed plasterering the walls and beams. - Completed the floor screeds as well. - Roof cover installed. - Started foundation of the pavings around. } Muallim House - Completed all the walling up to and above the ring beam. - Roof cover installed. - Window frames fixed.
|