Construction Progress Aug 09; Chengoni & Samburu: Project - Muallim Houses and Tailoring Classroom |
|
|
|
Construction Progress Report – August 2009
Centres: Chengoni & Samburu Project: Muallim Houses and Tailoring Classroom Samburu:
Three bed room Muallim House 1) Hardcore has been filled and compacting done. 2) DPM membrane has been laid 3) Anti-termite treatment has been done. 4) Formwork to side of slab done. 3) Concrete to the floor slab has been done. 4) DPC has been laid. 5) Superstructure walling upto the ringbeam has been built. 6) Stricking formwork to sides of beam 7) Steel has been fixed to the beam 8) Concrete to ring beam has been casted. |  | Chengoni: Tailoring 1) Strip foundation concrete has been casted 2) Steel fix to column base footings and starter columns steel 3) Concrete to column base has been casted 4) Foundation walling has been built 5) Formwork to sides starter of columns done 6) Concrete to starter columns has been casted 7) Back filling to sides of foundations done 9) Hardcore filling and compacting done Two Mualim Houses (N and S) 1) The entire houses have been plastered externally 2) The corners of the building have been made 3) The corners of the windows and doors have been made externallyAugust 2009 |