Renovation Progress Report - April 2009 (5) Print E-mail

Centre: Mackinnon Road

Project Masjid Refurbishment / Extension,
Construction of Four Classrooms and Muallim House

Masjid:

1. External block works done.
2. New windows placed in respective positions.
3. Roofing sheets were placed on steel trusses and gables in the prayer hall and verandah.
4. Plastering of walls both externally and internally in progress.

Image 

Image 

 MAIN ENTRANCE

 SIDE VIEW

 Image

 Image

 VERANDAH AREA

 INTERIOR AREA

 
Classrooms:

1. Vents already placed in the front of the rooms at the entrances.
2. Placing of tiles on the window sills externally was in progress.
3. The floor with red oxide done. 
4. Block work with plaster of the inbuilt cupboards was done.

Image 

Image 

 Image

 BACK VIEW

 FRONT VIEW

 INTERIOR AREA

 
Muallim House:

1. Placing of tiles on the window sills externally already done.
2. Vents were put at their respective places.
3. Paving slabs 600 mm x 600 mm placed all round.
4. The floor with red oxide done.
5. Toilet pit wall and slab over a 4.5 m/15 ft pit already constructed.
6. Construction of latrine/bath walls was in progress.

 Image

 Image

 INTERIOR VIEW

 EXTERIOR VIEW

 

Image 

 BATH / PIT LATRINE


Ventilation Improved Pit Latrine:

1. Toilet pit wall and slab over a 4.5 m/15 ft pit already constructed.
2. Construction of latrine walls for 4 cubicles was in progress.

Image 

 COMMON PIT LATRINE

April, 2009

 