Renovation Progress Report, Mackinnon Road Centre - March 2009 |
|
|
|
Centre : Mackinnon Road Project Masjid Refurbishment / Extension, Construction of Four Classrooms and Muallim House Masjid
a) The demolition work including removing the mabati roof cover has been completed. b) The excavated for column base pits has been done. c) The steel to base and starter columns has been fixed. d) The casting of concrete to column base and starter columns has been done.
Classrooms
- a) The block work for the superstructure walling up to the ring beam level has been done.
b) The setting of out shuttering for the ring beam has been started. c) The casting of concrete to all superstructure columns has been done.
| |  |
Muallim House :
| - a) The shuttering to side of slab has been removed.
b) The setting out of the building on the floor slab has been done. c) The superstructure walling has been started and has reached up to the window level.
| |
Common toilets  | They are still working on the toilet pit. |
|