Renovation Progress Report, Mackinnon Road Centre - March 2009 Print E-mail

Centre : Mackinnon Road

Project Masjid Refurbishment / Extension,
Construction of Four Classrooms and Muallim House


Masjid

Image  Image


  • a) The demolition work including removing the mabati roof cover has been completed.

  • b) The excavated for column base pits has been done.

  • c) The steel to base and starter columns has been fixed.

  • d) The casting of concrete to column base and starter columns has been done.

Image Image 


Classrooms

  • a) The block work for the superstructure walling up to the ring beam level has been done.

  • b) The setting of out shuttering for the ring beam has been started.

  • c) The casting of concrete to all superstructure columns has been done.
Image  Image


Muallim House :

Image  
  • a) The shuttering to side of slab has been removed.

  • b) The setting out of the building on the floor slab has been done.

  • c) The superstructure walling has been started and has reached up to the window level.

 

Image 

 

Common toilets

 ImageThey are still working on the toilet pit.  

 

 

 

 

 