Renovation Progress Report - February 2009 Print E-mail

 Centre : MACKINNON ROAD

 Project: Masjid Refurbishment / Extension,
Construction of Four Classrooms and Muallim House

Image 

MASJID

1. All the windows and doors have been removed. 

2. The toilets and ablution areas already demolished.

3. Roofing sheets removed. Truss being removed.

4. By next week all demolition work will Inshallah be complete.

5. The existing rear wall is moved by 4.3 m per the plan.
 

Image 

 Image

 Image

 Image

 Image

  


Classrooms:

Image 

1.  Blocks were already erected within the strip foundation.


2.  The ground/floor was leveled and compressed with hard core material, compression work still going on around the corridor.


3.  Steel columns to hold the ring beam already erected.

 

4.  All round outside ground ring beam already placed.
5. The compressed slab will be applied with anti pesticide (gladiator) already available in the material store.


6.  Inshallah cement/ballast/fiber mesh mixture casting with damp proof course (DPC) will be done by next week.  Fiber mesh already available at site.

Image 
 

Muallim House:

Image  Image

  1. Strip foundation trench already dug with perimeter trench excavation of all the internal portions.

  2. Blocks were almost laid within the excavation trench to ground level.

  3. Some areas hard core material was laid and compressed.

 

Common Toilets:

 Pit for Ventilation Improved Pit Latrine dug to around
5 feet deep, still to continue digging further.