Renovation Progress Report, Chengoni and Samburu - February 2009 Print E-mail

Project:    Four Classrooms, Muallim Houses And Tailoring Classroom

Samburu:

 

Muallim House:

1. Strip foundation trench already dug with perimeter trench excavation of all the internal portions.
2. Materials delivered at site aggregate (kokoto) 16 tonnes, sand 20 tonnes and 100 blocks.

Photographs of progress of Muallim House

 Image Image


 
Chengoni:


 
Muallim Houses: 

 
  1. On the eastern side of the House centre strip foundation trench with perimeter excavation trench for internal portions already dug.

  2. The blind topping done with hardcore is already applied with anti pesticide and floor casting of kokoto/fiber mesh/cement mixture.

  3. On the western side excavation trench dug and blocks erected to ground level.  Floor already compressed with hardcore awaiting floor slab casting.

  4. Toilet pit for one mualim house dug to between 12-15 feet deep


Photographs of progress of Muallim House (Eastern and Western side)

 

 

 

Image 

 Image

 

Tailoring Classroom:

  1. The strip foundation excavation trench already dug to the verandah wall with portions showing positions for columns.

  2. Next is laying of foundation slab.

Photographs of progress of Tailoring Classroom
 
The works are progressing well and expected to be completed as per schedule. 

 Image

February 2009    

 

 