Moyeni Construction Progress Report October 2008. Print E-mail

 

Project in Final Stages of Completion.

 Masjid :

 Imagea) The floor screed has been laid to the entire Masjid floor to both ladies and gents side.
b) The ceramic tile finish has been put in the ablution areas to floor and wall both sides.
c) The internal plumbing to both sides has been done.
d) All electrical power and light points have been placed. 
 Image
 Imagee) The plastering works has been completed.
f) The external paving slabs have been laid.
g) The 1st coat to the plastered wall has been applied.
h) The door shutters to the 2 No. main doors to the prayer hall, complete with aldrob, stopper and rubber stopper have been installed.
i) The window shutters complete with furniture; stopper and window stay have been installed.
j) The grill doors at the entrance have been fixed.
k) The tank plinth has already been built and ready to receive the water tanks.
l) The down pipe from the gutter has been put to place and ready to connect to the water tank.

 

 

Classrooms :

 

a) The plastering of the verandah arches and columns have been completed.
b) The cupboards completed with in frame, shutters and shelves.
c) The door shutters with aldrob and rubber stopper completed.
d) The window shutters complete with brass stoppers and window stay.
e) The 1st coat of paint has been applied to the entire building.
f) The paving slabs have been laid around the building block.
 Image
 Imageg) The floor screed has been laid in the classrooms including the verandah.
h) The timber rail to the writing board and chalk rail have been fixed.
i) The timber rail with hooks for hanging charts and other teaching aids have been installed all around the classroom as per specification.
 Image

 

 

Muallim House :

 

 Imagea) Wall plastering has been finished to the entire muallim house.
b) The roof structure has been installed.
c) The louver frames complete with louver glasses have been fixed.
d) The door shutters to all the rooms have been fixed.
e) The floors creed to the entire house has been laid.
f) The paving slabs around the building have been laid.
g) The substructure walling to the Muallim Toilet has been built.
h) The floor slab to the Muallim Toilet has been casted.
 Image

 

 

Pit Latrines :

 

 

4 Nos Ventilation Improved Pit Latrines has been completed.

 Image

October, 2008

 