Samburu Construction Progress Report; July 2008 Print E-mail

Masjid :


• The doors to Masjid entrance both of gents and ladies have been fitted.
• The tile work at ablution areas is done for both ladies and gents.
• The floor screed has been laid to the entire Masjid.
• The entire Masjid has been painted in 2 coats paint including gloss paint skirting internally.
• Water tanks have been installed on the tank plinths, harvesting rain water and connected to the ablution areas.


Image Image Image

Classrooms:


• Plastering to the arches and columns at the classrooms verandah have been completed.
• Roofing sheets fitted to all the classrooms and the corridor in the front.
• Frames to the in-built cupboards have been installed including fixing of shelves and shutters.
• Door shutters to the four classrooms have been installed.
• All window shutters have been fixed. 
• The corridor floor screed has been done.

Image Image Image

Toilet:


• Walling to the toilet pit has been done.
• The top concrete slab has been casted.
• The sides of the pit latrine have been backfilled.