Samburu Construction Progress Report; July 2008 |
|
|
|
Masjid : • The doors to Masjid entrance both of gents and ladies have been fitted. • The tile work at ablution areas is done for both ladies and gents. • The floor screed has been laid to the entire Masjid. • The entire Masjid has been painted in 2 coats paint including gloss paint skirting internally. • Water tanks have been installed on the tank plinths, harvesting rain water and connected to the ablution areas.

Classrooms: • Plastering to the arches and columns at the classrooms verandah have been completed. • Roofing sheets fitted to all the classrooms and the corridor in the front. • Frames to the in-built cupboards have been installed including fixing of shelves and shutters. • Door shutters to the four classrooms have been installed. • All window shutters have been fixed. • The corridor floor screed has been done.

Toilet: • Walling to the toilet pit has been done. • The top concrete slab has been casted. • The sides of the pit latrine have been backfilled.
 |