Samburu Construction Progress Report April 2008 Print E-mail

Samburu Progress:

Masjid

  1. Laying of red oxide floor screed to the entire Masjid including skirting is finished.
  2. Built 3 No. Masonry tank Plinth in coral blocks and plastering. One tank plinth is pending.
  3. Paving slabs has been laid all around the Masjid ; 2ft to the side and 4ft to the front. Filling of the joint and finishing of the sides have to be done.
  4. Dug the common toilet on the right position as we pointed out up to 7ft deep.
  5. The rainwater tank pipe to serve the ablution area has been connected.
  6. The taps to the ablution areas for both ladies and gents has been fixed.

 

Image Image

 

Image Image



Classrooms

  1. All the existing mabati roof cover to four classrooms has been removed.
  2. The ring beam all round the four classrooms has been casted.
  3. The gable ends above the ring beam, which was demolished to run an r.c beam has been built.
  4. Plastering  the gable and other walls externally has finished.
  5. Cast Concrete columns has been erected on the verandah and run a beam above them.
  6. Some trusses were prepared and are ready to start roof covering early this week.
    Window frames in the classrooms has been installed.
  7. One classroom has been ventilated.


 Image Image Image

 