Samburu Construction Progress Report March 2008 |
|
|
|
Samburu Progress: Masjid a) Floor repairs to the gutter done, to receive quarry tiles finish. b) Constructed the tank plinth up to the level of the ablution approx. 4ft high. c) Demolished the floor finish to put new floor. d) Removed the wall tiles at the ablution. e) Removed the double doors at the Masjid create an opening for the new door. f) Built wall around the mosque to lay paving slabs. g) Laid out the pipe conduits for the electrical work. h) Started pit excavation for the communal toilet. i) Demolished the existing ladies toilet block at the front of the Masjid.  Classrooms a) Removed the existing ceiling to the 2 No. rear classrooms. b) Removed the roof of the rear 2No. Classrooms. c) Partly demolished the side wall (which was falling off) to the rear classrooms and cast in an r.c beam as per the Engineer’s advice. d) Casted a structural column at the side corner of the rear classroom. e) Excavated trench and cast foundation concrete for the paving slabs.
  
|