Construction / Renovation Progress Report; June 2008 |
|
|
|
Construction / Renovation Progress Report Moyeni Centre - June 2008 Project: Masjid, Four Classrooms and Muallim House Masjid : • All RC Columns have been erected upto beam level. • The RC Ring beams to the perimeter wall of the Masjid have been casted. • The party walls partitioning the gents and ladies prayer hall, verandah and ablution area have been built. • RC slab has been casted in the ablution area, including the water drainage channel. • The walling to the gable ends above the ring beam has been built. • The shuttering of the RC beam is in progress. 
Classrooms : • Columns of the entire block have been erected. • Walling to the structure has been built including the gable ends above the beam. • The RC beam to the perimeter walling of the classroom have been casted.  Muallim House: • The ground floor slab has been casted. • Termite Treatment has been made. • The walling to the entire building structure including the gable ends has been built. • The ring beam to the perimeter wall and lintels to the internal openings have been casted. • The Muallim house building structure is ready for roof fixing.  |