Moyeni Construction Progress Report; May 2008 |
|
|
|
Construction Report – Centre Moyeni - May 2008 Project: Masjid, Four Classrooms and Muallim House Masjid The roof cover and the entire timber framework to the existing Masjid has been removed. The extension of the Masjid has been set out and line marked. Excavation of the foundation trenches to the extension of the verandah has been done. Excavation for the column base pits is being done and RC Columns are being erected. 

Classrooms - Classroom blocks have been set out and line marking the area.
- Foundation trenches for the entire classroom block have been excavated, 2 ft deep.
- The columns for the entire block have been set.
- Excavation of column base pits have been done and line marking the position for the RC columns has been done for steel reinforcement.
- Ground ring beam concrete has been done.
- Layers to the perimeter wall around the classrooms block is in progress. Foundation has been laid and sub walling done.
- Preparations on to fill in hardcore material ready for the ground floor slab. Superstructure walling is in progress.
 Muallim House Muallim House area has been line marked and excavation of foundation trenches for the entire building has been done.
Pit Latrine The excavation of pits (6ft deep) for both common toilets and Muallim House has been started. 
|